SAPCA update
Delivering a successful project - Step 1: Preparation and planning

In 2019, we’ll feature a series of four quarterly articles, in which experts from SAPCA outline the steps required to ensure a successful facility project. In the first of the series, SAPCA project manager Colin Corline explains the importance of preparation and planning


Each sports facility project begins with a great idea. It may be one borne out of a specific need, such as a governing body’s Strategic Plan, or a local authority needing to improve its facility infrastructure. Or it could be a sports club or school wanting to upgrade its facilities in order to attract more people to play sport.

Having a great idea marks the beginning of the project journey – but the first real step is to come up with a great plan.

Development of A brief
Developing a facility can be a daunting prospect with so many variables to consider. Whatever the project, however, it is important to realise that the principles are the same – and that creating a strong project brief in the early stages is essential.

The project brief should encompass all elements of the project – from the specific requirements of the sporting and non-sporting facilities and the type of sports to be played, to the perceived business case and any budgetary constraints. You also need to consider local insight and the demographics that would support the project, as well as local authority, NGB or sports council backing.

When developing the project brief, it is essential that you engage with a wide range of partners to ensure the initiation document considers all the relevant elements of the project at an early stage. This is where SAPCA can help. SAPCA members construct the vast majority of sports facilities across the UK, and at this early project development stage members of SAPCA’s Professional Services Group can offer design and technical expertise on all aspects of project planning. Having specialists assist you at an early stage will help you develop a clear and comprehensive brief.

Once the document is complete, the next phase is to circulate the project brief within the wider community, in order to gauge support with the relevant bodies and to allow the conceptual idea of the brief – where applicable – to be enhanced and developed.

THE application
The development of a detailed design and planning application can potentially be the most important phase of the project. Here is a useful list of things you need to consider:

• The business plan, both for the delivery of the project and for the ongoing development of the venue, should be developed at this stage. This is to ensure you consider and understand the impact of the project and how the new (or upgraded) facility will impact on the potential growth of participation and the retention of existing players.

• There will be a need to develop a cost plan for the project development, to allow budgets to be set and to allow you, if applicable, to seek partnership funding.

• In order to support the development of the cost plan, it is likely that you will need to engage design consultants to produce drawings and get the development through the required site surveys.

• Engage with the local authority planning department to assess the viability of the project from a planning perspective. This may also require further assistance from consultants to aid the planning application with required reports, surveys and layout drawings.

• Undertake discussions with local residents, community groups and any other relevant interested parties to garner support for the project.

• Use SAPCA’s web-based project journey information to aid the development of the project through case studies and technical information.

• Use information from the relevant National Governing Body’s facility development website to aid the development of the project.

• Play-test any relevant products or playing surface products to aid understanding of the sporting needs and to aid the formulation of the design.

Once you have completed this process, you should have solid plans in place for the project. While the plans can be tweaked and fine-tuned at a later stage – through engagement with NGBs, consultants and contractors – following this guidance you should have plans that offer a solid base for a successful project.

For more information on SAPCA, its Technical Programme or safety at sports facilities in general, contact us at: [email protected] or 024 7641 6316 www.sapca.org.uk

SAPCA project manager Colin Corline says strong planning is key to success
Project managers should undertake discussions with local residents and community groups to garner support for the project Credit: © shutterstock/Kzenon
FEATURED SUPPLIERS

Spa and wellness industry to reunite at Forum HOTel&SPA 2024
The 16th edition of the esteemed international spa and hospitality industry event, Forum HOTel&SPA, is rapidly approaching, promising an immersive experience for attendees. [more...]

Crafting luxury: Beltrami Linen's bespoke spa solutions
Beltrami Linen’s approach to the world of spa is underpinned by a strong emphasis on bespoke design, where close collaboration with customers and their designers is always of the utmost importance. [more...]
+ More featured suppliers  
COMPANY PROFILES
Cariitti Oy

Cariitti is a Finnish family business founded by Kari Ruokonen in 1998 that offers versatile lightin [more...]
Sommerhuber GmbH

Sommerhuber specialises in the manufacturing of heat-storing ceramics for spas. [more...]
+ More profiles  
CATALOGUE GALLERY
 

+ More catalogues  

DIRECTORY
+ More directory  
DIARY

 

22-24 Apr 2024

UK Aufguss Championships

Galgorm Resort, York,
23-25 Apr 2024

ISPA Conference 2024

Phoenix Convention Center, Phoenix, United States
+ More diary  
 
ABOUT LEISURE MEDIA
LEISURE MEDIA MAGAZINES
LEISURE MEDIA HANDBOOKS
LEISURE MEDIA WEBSITES
LEISURE MEDIA PRODUCT SEARCH
 
SPA BUSINESS
SPA OPPORTUNITIES
SPA BUSINESS HANDBOOK
PRINT SUBSCRIPTIONS
FREE DIGITAL SUBSCRIPTIONS
ADVERTISE . CONTACT US

Leisure Media
Tel: +44 (0)1462 431385

©Cybertrek 2024
Uniting the world of spa & wellness
Get Spa Business and Spa Business insider digital magazines FREE
Sign up here ▸
News   Products   Magazine   Subscribe
SAPCA update
Delivering a successful project - Step 1: Preparation and planning

In 2019, we’ll feature a series of four quarterly articles, in which experts from SAPCA outline the steps required to ensure a successful facility project. In the first of the series, SAPCA project manager Colin Corline explains the importance of preparation and planning


Each sports facility project begins with a great idea. It may be one borne out of a specific need, such as a governing body’s Strategic Plan, or a local authority needing to improve its facility infrastructure. Or it could be a sports club or school wanting to upgrade its facilities in order to attract more people to play sport.

Having a great idea marks the beginning of the project journey – but the first real step is to come up with a great plan.

Development of A brief
Developing a facility can be a daunting prospect with so many variables to consider. Whatever the project, however, it is important to realise that the principles are the same – and that creating a strong project brief in the early stages is essential.

The project brief should encompass all elements of the project – from the specific requirements of the sporting and non-sporting facilities and the type of sports to be played, to the perceived business case and any budgetary constraints. You also need to consider local insight and the demographics that would support the project, as well as local authority, NGB or sports council backing.

When developing the project brief, it is essential that you engage with a wide range of partners to ensure the initiation document considers all the relevant elements of the project at an early stage. This is where SAPCA can help. SAPCA members construct the vast majority of sports facilities across the UK, and at this early project development stage members of SAPCA’s Professional Services Group can offer design and technical expertise on all aspects of project planning. Having specialists assist you at an early stage will help you develop a clear and comprehensive brief.

Once the document is complete, the next phase is to circulate the project brief within the wider community, in order to gauge support with the relevant bodies and to allow the conceptual idea of the brief – where applicable – to be enhanced and developed.

THE application
The development of a detailed design and planning application can potentially be the most important phase of the project. Here is a useful list of things you need to consider:

• The business plan, both for the delivery of the project and for the ongoing development of the venue, should be developed at this stage. This is to ensure you consider and understand the impact of the project and how the new (or upgraded) facility will impact on the potential growth of participation and the retention of existing players.

• There will be a need to develop a cost plan for the project development, to allow budgets to be set and to allow you, if applicable, to seek partnership funding.

• In order to support the development of the cost plan, it is likely that you will need to engage design consultants to produce drawings and get the development through the required site surveys.

• Engage with the local authority planning department to assess the viability of the project from a planning perspective. This may also require further assistance from consultants to aid the planning application with required reports, surveys and layout drawings.

• Undertake discussions with local residents, community groups and any other relevant interested parties to garner support for the project.

• Use SAPCA’s web-based project journey information to aid the development of the project through case studies and technical information.

• Use information from the relevant National Governing Body’s facility development website to aid the development of the project.

• Play-test any relevant products or playing surface products to aid understanding of the sporting needs and to aid the formulation of the design.

Once you have completed this process, you should have solid plans in place for the project. While the plans can be tweaked and fine-tuned at a later stage – through engagement with NGBs, consultants and contractors – following this guidance you should have plans that offer a solid base for a successful project.

For more information on SAPCA, its Technical Programme or safety at sports facilities in general, contact us at: [email protected] or 024 7641 6316 www.sapca.org.uk

SAPCA project manager Colin Corline says strong planning is key to success
Project managers should undertake discussions with local residents and community groups to garner support for the project Credit: © shutterstock/Kzenon
LATEST NEWS
Six Senses La Sagesse launches with lagoon-fronted spa inspired by Caribbean fishing villages
Six Senses has announced the grand opening of its first-ever property and spa in the Caribbean, called Six Senses La Sagesse.
Basic-Fit trials corporate wellness drive across its Spanish clubs
Basic-Fit has signed up to trial the Wellhub network across its recently expanded Spanish network, giving access to subscribers and enabling them to use all 152 of its Spanish clubs.
Go Fit CEO, Mário Barbosa, unveils expansion plans in this month’s HCM
Having redefined the model of public-private collaboration in Spain, Go Fit is now expanding into Italy and has ambitious plans to grow its estate, memberships and profits.
US$60m Zion Canyon Hot Springs project breaks ground in Southern Utah
A brand new desert hot springs oasis, called Zion Canyon Hot Springs, is set to open in Southern Utah in Q3 of 2025.
Dedicated recovery clubs tipped to become a trend
Recovery, social wellness and longevity were talking points at the recent PerformX Live, tipped by many speakers as upcoming trends, while the exhibition halls featured infrared saunas, compression therapy and ice baths.
Research: Kundalini yoga provides cognitive benefits to postmenopausal women at risk of Alzheimer's
A new study by UCLA Health found Kundalini yoga provided several benefits to cognition and memory for older women at risk of developing Alzheimer’s disease.
New lakeside spa oasis set to open at The Ritz-Carlton-Reynolds, Lake Oconee
Luxury lakeside retreat The Ritz-Carlton-Reynolds, Lake Oconee in Georgia, US, is gearing up to unveil its new-look destination spa this May following a comprehensive makeover.
Europe's premier Evian Spa unveiled at Hôtel Royal in France
Europe’s first Evian Spa has opened at the five-star Hôtel Royal in Evian-les-Bains, France – the birthplace of the mineral water brand Evian.
Atzaró Okavango Camp and wellness retreat to launch in Botswana wildlife haven
A boutique safari and wellness escape will open in Botswana’s wildlife-rich Okavango Delta this May, marking the latest venture from Ibiza's Atzaró Group.
Global summit will bring together industry leaders in health, fitness and wellness
Global publishing outfit, Leisure Media, has announced details of its new annual conference for decision- makers across the health, fitness and wellness markets. The event – the HCM Summit – will be held at the QEII Conference Centre in Westminster, London on 24 October 2024, with pre-summit events the day before.
Ronaldo crashes the app store with launch of new wellness, fitness and health app, Erakulis
Portugese footballer, Cristiano Ronaldo, has launched a health and wellness app that harmonises advice on fitness, nutrition and mental wellness in one seamless experience.
Research: Timing of exercise more important than workout type or length in ensuring health benefits
Spas which offer a fitness element might benefit from thinking about the timings of sessions, according to new research from Leiden University Medical Center in the Netherlands.
+ More news   
 
FEATURED SUPPLIERS

Spa and wellness industry to reunite at Forum HOTel&SPA 2024
The 16th edition of the esteemed international spa and hospitality industry event, Forum HOTel&SPA, is rapidly approaching, promising an immersive experience for attendees. [more...]

Crafting luxury: Beltrami Linen's bespoke spa solutions
Beltrami Linen’s approach to the world of spa is underpinned by a strong emphasis on bespoke design, where close collaboration with customers and their designers is always of the utmost importance. [more...]
+ More featured suppliers  
COMPANY PROFILES
Cariitti Oy

Cariitti is a Finnish family business founded by Kari Ruokonen in 1998 that offers versatile lightin [more...]
+ More profiles  
CATALOGUE GALLERY
+ More catalogues  

DIRECTORY
+ More directory  
DIARY

 

22-24 Apr 2024

UK Aufguss Championships

Galgorm Resort, York,
23-25 Apr 2024

ISPA Conference 2024

Phoenix Convention Center, Phoenix, United States
+ More diary  
 


ADVERTISE . CONTACT US

Leisure Media
Tel: +44 (0)1462 431385

©Cybertrek 2024

ABOUT LEISURE MEDIA
LEISURE MEDIA MAGAZINES
LEISURE MEDIA HANDBOOKS
LEISURE MEDIA WEBSITES
LEISURE MEDIA PRODUCT SEARCH
PRINT SUBSCRIPTIONS
FREE DIGITAL SUBSCRIPTIONS